Monday, June 7, 2010

Monday, DAY 64

Good work completed today.
WOODLAND CIRCLE: Several storm inlets were installed today. Also, road reconstruction made it about halfway down the interior block. They hope to finish that road reconstruction tomorrow---though rain is also expected so be cautious about that.
ROXBURY ROAD: Water main was just about completed when I left that area at mid-afternoon. I would think that it got completed today. That means that the new main will begin getting tested for pressure, filled, and then water sampled very soon. Once all tests are completed, the three residential services will be done.
NEW CASTLE/CHARING CROSS: Based on weather, these two roads should start as a crew is made available. The Village has all permits necessary to begin work in the upper bluff.
Kensington sidewalk and driveway work was also a focal point today. Concrete was scheduled for tomorrow but based on weather, we may not see them.

Hope for clear weather.....