Monday, June 21, 2010

Day 75 (Fri) - Day78 (Mon)

Last Friday, we made progress with water main installation on New Castle. This particular water main keeps crossing the sanitary main so it is slow and tedious work. There is not alot more distance to cover on New Castle with water main, so once that is completed, they will move over to Charing Cross.

We are still needing to get Roxbury Road rebuilt. The extreme wet conditions and then other tasks that came up, prevented this from getting completed last week. Hopefully, they get that tackled today.

Anticipate ongoing preparation and pouring of driveway aprons, sidewalks, and additional road prep for this week. You will also see rough grading of restoration areas getting started in the lower bluff this week!!

I will be gone for this week and early of next week. Tom will be sending me updates if there is newsworthy information to get posted.