Thursday, June 24, 2010

Day 79 (Tues) - Day 81 (Thur)

So, as I am out east, work progresses; this is info from a couple days ago so work has advanced from that update....but,this is what I have to offer:

Roxbury street is built out. Work on sidewalk on Roxbury is continuing with removal and prep for new concrete.

Woodland circle concrete is in. Lakewood Blvd concrete and aprons are in.

Lower Bluff....right now, we are tentative for Frank Brothers Asphalt to come into the Village to put down the binder coat of asphalt the week of July 5th. After binder asphalt, the contractor will finish the landscaping restoration and then, the final layer of asphalt will be completed.

New Castle: Water Main is in. Services are connected in the 200 block. If testing is not already received for the balance of New Castle, it should be completed soon. Once completed, the balance of services will be switched over.

Charing Cross: Water Main was being worked on earlier in the week and if it is not completed, should be done soon. Then, main testing and transer of services to the new main.