Thursday, June 10, 2010

Day 67

Rain Rain come again on Friday!! Or so it appears. We shall see if we can get any work completed tomorrow or if we get rained out again.

Today, Woodland Circle road base was completed. That will sure make any rain this weekend easier to take!! It does not mean that it will be perfect though, so still drive cautiously.

The Road Crew then went down to get the intersection of Kensington and Roxbury rebuilt. However, they cant rebuild Roxbury until residential services are completed next week. The test sample for the Roxbury main was sent in and should be back tomorrow. Services will be completed on Monday. You should avoid driving on Roxbury between Lakewood and Kensington. A Cadillac Escalade found that out the hard way. Yup, buried up to the floor boards.

A good amount of sidewalk and some driveway aprons got poured on Kensington today.

Water main crews worked installing main westbound on New Castle today. There was a stretch of Sanitary Sewer that they had to dig under so that slowed progress but they were heading toward Charing Cross at lunch time today.