Thursday, June 17, 2010

Day 73 (Wed) & Day 74 (Thur)

On Wednesday, there was some work done on sanitary sewers on Woodland Circle. However, the dump pit where the contractor takes much of their 'spoils', was closed due to all the rain we have gotten recently.

In fact, that pit was also closed for much of today (Thursday), so the rebuilding of Roxbury Road was delayed until that pit could be opened later in the day today.

Water Main work continued on New Castle. Another water main break occured up there today so that slowed their progress a bit. This is the 2d break the contractor has experienced on this section of road.

The concrete contractor is expected in the Village tomorrow and will be pouring more driveway aprons, sidewalks, and curbs.

We learned yesterday that the sub-contractor doing the asphalt paving will NOT be willing to do any private driveway work. This means that if you have an asphalt driveway, you will need to get your own asphalt contractor to do your driveway IF you wanted the entire driveway completed. The contractor WILL do that portion of your driveway that we remove---usually back to a saw cut on the existing driveway. We are working with another local contractor to allow residents to get the best price possible should they want to replace their entire driveway. We will be meeting with that contractor tomorrow and we will come up with more information and let you know about that tomorrow.