Tuesday, May 18, 2010

Day 44; Tuesday Concrete Already???

I knew that Monday was a good weather day, but what a bunch of progress. The water main crew on Woodland Circle on Monday put in 330' of water main. That is phenomenal work.

Similar progress was made today. We added another crew onto Cambridge to work on residential services. This means that the water tested clean on Cambridge so they are now attached to the new main. Residential Services also continued southbound on Kensington.

Road reconstruction also continued; there were actually two road reconstruction crews in the Village today to begin preparation for the concrete contractor to arrive yet this week.

The concrete contractor is expected on WEDNESDAY to begin work. We anticipate driveway aprons, curbs, etc to be getting poured yet this week. This will take place in those areas where there is no pipe work or other road work left. Kensington in the 300 and 400 blocks, Fisk, etc.

Keep you attention as conditions are changing fairly quickly.

I will have new details soon on the move to the upper bluff; that too is coming quickly so stand by up there.......