Monday, May 17, 2010

Day 43; Beautiful week ahead

Crews were back at it today working on those areas that we anticipated in my post from last Thursday. Tomorrow, another crew will be in Village working on a few last connections to the water main at Cambridge and Lakewood. Services will then be completed and the balance of the road will be rebuilt. You may notice that Lake Anderson is now gone, replaced with the start of a rebuilt road!!!

Our friends on Woodland Circle are receiving water main installation this week. They will also then move to storm system enhancements. As a reminder, there is no parking on any street directly under construction. All we ask is that you work with the contractor to get your car moved to a reasonable location.

I should have some new details on the upper bluff construction starting date soon. Stand by and watch for that information.....