Day 33, Today--Friday 5/7 is quite easy....rain, and no, or very minimal work.

Day 32, Thursday, showed progress in the water main installation on Cambridge Road. They have completed a bit more than half of Cambridge. I can tell you however in that construction, that we are finding some horribly soft base under the roads. This makes road rebuilding more difficult and temporary roads even more difficult to make passable for traffic. If you go by Cambridge Road, you will notice that it is mostly closed down.
This crew will begin water main installation on Woodland Circle after Cambridge Water Main is completed. Work will begin at the south intersection with Kensington and will proceed north.
Other work on Thursday included road reconstruction southbound on Kensington that has reached Oxford. Residential services south of Oxford are now ready to be completed as the new main has passed the water tests. One service was already completed as crews fixed a break in the old water main. Others will continue next week.

Tentative plans to complete work in the Lakewood at Fisk Place intersection is scheduled for the week of May 17th. Please recognize that traffic on Lakewood will be affected. We anticipate one lane through this area and possibly having the need for a flagman. Consider this if you pass this area frequently, as you may want to consider leaving the Village through the outer drive of Farwell. More information will be posted as we get closer.