Day 99--MONDAY 7/12 PAVING CHANGE!!!

Good Morning.

Many residents in the lower bluff are anticipating the final layer of pavement for tomorrow. Earlier today, we learned that the paving contractor had a change to their schedule that will allow them to come to Maple Bluff TODAY. So, we anticipate seeing Frank Brothers Contractors in Village some time after lunch. Staff is making their way around the Village and knocking on doors to inform residents of the change.

Because they only have a 1/2 day to work here today, Frank Bros will focus on paving the following streets for today:
  • Fisk
  • Woodland Circle
  • Cambridge
On Tuesday, Kensington will be paved.

Please note that Paving is subject to the weather. If there is rain falling or wetness on the ground, there will be no paving.

We appreciate your patience in the adjustment of the schedule.