Friday, July 16, 2010

Day 101 (Wed) thru Day 103 (Fri)

A great week of progress!! As of mid day today, let me recap where we are.

Lower Bluff:
  • Paving Done; this includes many asphalt driveways. The Village may have 1 or 2 left to complete due to some structural issues that we have to deal with in the driveway. If you are doing your own driveway, then you are not completed yet.
  • Finish Landscaping. Some start to this but the majority of the work should be done next week.
Upper Bluff:
  • New Castle: Road built, some storm work complete, more being done today.
  • Charing Cross: Road Built
  • McBride: Water main complete. Mains tested and clear. Residential services completed. Road built from Summit to New Castle and now, working from LeRoy up the hill; but they will probably not finish the road building on McBride today. Also on McBride at New Castle, they are installing a rather large storm system box today.
  • Magdeline: Pipe crew has started water main installation and is down the street from McBride toward Butternut. That same pipe crew had to pull off to work on residential services and now, putting in storm system. Also on Magdeline, 5 or 6 residences will get a letter today about the change in how they receive their water. That will take place next week.
The Electric Utility undergrounding project continues on Farwell. Please be careful of the trucks in that area!!!

Have a good weekend!!!