The water main pipe crew was able to install approximately 250 feet of pipe today!! That is great progress. They are just slightly north of the Kensington/Cambridge/Woodland Circle intersection. Early tomorrow, they will be starting with a new hydrant installation and then continuing south from there into the 200 Block.
The storm sewer pipe crew made good progress today as well, basically cover the other half of the block of Fisk Place. For tomorrow, they will be doing additional work at the storm inlet locations on Fisk. This is alot of small, tedious work to complete that storm system.
Please continue to adhere to the efforts to avoid the work zones. Residents have found difficult travels during the work day when the crews have not yet graded or smoothed out the roadway.
For those residents in the 300 block of Kensington Drive or on Woodland Circle, your best ingress/egress tomorrow may be through the MBCC parking lot and out the drive going to Lakewood. Good Luck!!!

No comments:

Post a Comment