Wednesday, September 1, 2010

Wednesday 9/1 Day 150 (Date for Paving!!)

Only a moment to report tonight...so here goes a quick summary:

All water main and all residential services are on new water main on Farwell and the entire upper bluff project zone.

The road rebuilding on Farwell is down to several hundred feet in the 400 block. That should be completed tomorrow. For residents on Farwell, that work zone window has shrunk for road building, but there are still some areas where storm system crossings are being made so access will still be limited tomorrow.

MG&E Gas main installation on Farwell is still taking place but we hope that they will complete that project in the next week or so.

For residents on McBride, Magdeline and Summit, the concrete contractor is scheduled to be in the Village tomorrow (Thursday). If you have a concrete driveway, you should be sure to get all of your vehicles out of the driveway/garage before the driveway gets poured.

A tentative date for the paving contractor to return to the Village is Friday Sept 10th and Monday, Sept 13th. On the 10th, we would anticipate binder on McBride, Magdeline and Summit and a Surface layer on New Castle, Charing, and Laurel. The 13th, would tentatively bring the binder surface for Farwell!! Still some work to do to prep for that, but that is still the tentative plan; lets hope it works that way.

Restoration work will continue on all the upper bluff project zones. Stand by for changing conditions!!! Good night.