Due to some less than desirable weather last week, we have been told that the concrete contractor will not be in the Village until Thursday in stead of Wednesday.

Also on Thursday, we are anticipating that Frnak Brothers will be coming into the Village to pave in the afternoon. This paving will be focused on the Surface of New Castle and Charing Cross. You should plan that once these streets are paved, we will need to keep traffic off the road for numerous hours so plan to park away from your home until later that evening. We are planning to open the road after 8pm.

Binder paving on McBride, Magdeline and Summit will either take place on Friday or Monday. However, there will be limited closure for the binder layer of pavement.

Storm system connections were concluded today. There is still some electrical undergrounding and gas main projects for MG&E taking place around the entire Farwell zones so stay alert for those changing conditions.
.