Well my friends, work has continued. The last 2 weeks, there has been direct communication with the residents within the construction zone. The direct commuication was the result of a fluid schedule on the work that was being completed.
Let me bring everyone up to speed on where we are.
Surface blacktop was put down on McBride, Magdeline and Summit last week. Asphalt driveways were completed in that section yesterday. Restoration of grass will continue with hydra seeding taking place next week.
Farwell Drive received binder asphalt yesterday.
We expect the SURFACE on Farwell to be put down on MONDAY!! Notices will be delivered to Farwell homes today that they will need to have cars out of driveways by 6a on Monday morning. The asphalt contract intends to apply "Tac"--a very sticky material used to adhere the two layers of asphalt together, so they can begin paving by 7am. If you drive over the "tac", it may get onto your vehicle and be VERY difficult to get off!!
Asphalt driveways on Farwell will get their surface material next Wednesday and Thursday. Restoration will continue on Farwell all of next week as well.
Friday, September 24, 2010