Monday, October 18, 2010

DAY 198 Mon Oct 18th

Most of you have had little contact with the infrastructure contractor the past couple weeks; but, they have still been here. Their work has mostly consisted of the final stitching of putting the Village back together again.

Almost all areas have received Hydra-seeding. They are finishing a few other restoration projects but mostly just cleaning up signs and other miscellaneous stuff around the Village. There are a few punch list items that are still being remedied. But, we anticipate a skeleton crew showing up today but not staying around the Village too long this week.

For those of you who must drive through the Lakewood Blvd corridor, we are trying to get some prices from either of the two contractors in the Village to get those road segments repaired.

If you have not taken the time to look over the new pond area between the Village and the MBCC tennis courts, that project has progressed quite far as well. The pond is dug out completely and they have stopped pumping water out of it so it is slowly filling in with ground water and several springs that are feeding it. The pipe to the lake is still blocked so we are not getting water yet flowing from the lake to the pond.

The storm water pipe thru the MBCC driving range is installed. There are still a few more storm structures in various parts of the project, and, the connection near the maintenance shop that need to be installed. Another week or two on this project and they should be wrapping up as well!!!

As a reminder, once construction is done, I will start using the BLOG for ongoing Village News, so stay tuned to this communication method for ongoing information!!