Sunday, August 8, 2010

Day 123 (Thu)/Day 124 (Fri)

On Both Thur and Fri, work continued on water main with the crew getting past Summit and near the hairpin turn on Farwell--so they are still in the 700 block.

The road crew was rebuilding road on Thursday with Magdeline having a fair amount of road now rebuilt. They are only 3-4 houses from reaching Summit Drive!! ON Friday, the road crew was doing a variety of house cleaning tasks around the project zones; those are miscellaneous jobs to help keep the areas as tidy as possible. So, there was no road building going on Friday.

We anticipate seeing the asphalt contractor in the Village some time early this next week for Binder on New Castle, Charing Cross, and Roxbury. There was discussion at the construction meeting on Thursday that we may be able to have the "Surface" asphalt put down relatively quickly then and hopefully begin the restoration on New Castle and Charing Cross within a week or two. As these plans get more detailed and firmed up this week, I will keep you informed!!

No comments:

Post a Comment