Friday, March 26, 2010

Construction Info

Construction:
A Pre-Construction meeting was held yesterday, 3/25, with staff, the Contractor, utilities, Bus Companies, and other interested parties in attendance. Coordination between all of these entities is strong and we hope to keep these relationships just as strong throughout this construction process.

Starting next week, the week of March 29th, you will begin to see more mobilization. Heavy equipment will be arriving and staging, pipe and other miscellaneous construction materials will also be showing up.

Construction will start the week of April 5th. We anticipate that the roads in the Lower Bluff project zones will be removed that Monday. This will include Kensington, Cambridge (10 Block), Woodland Circle, and Fisk Place.

On Tuesday, will be start of installation of Storm sewer on Fisk and WaterMain on Kensington from North to South.

The overall schedule for the Lower Bluff appears to have a mid June completion.

The Upper Bluff project zones remain under a DNR imposed suspension until clearance is given. No schedule is available yet because of this halt.

Please stay in touch regarding these projects; we will share any information that we have regarding schedules or specific impacts to your property!!

No comments: